DKEnerginet
TR 3.3.1 — Technical Regulation for Energy Storage
127 grid connection requirements for non-synchronous BESS plants (Type C and D), organized by functional category. Each requirement is tagged with the equipment scope responsible for delivering it. Denmark operates in two synchronous areas — DK1 (Continental Europe) and DK2 (Nordic) — with different frequency control parameters in each.
Type categories (TR 3.3.1 §2)
Type A
Up to 125 kW
Type B
125 kW – 3 MW
Type C
3 – 25 MW
Type D
≥ 25 MW or ≥ 110 kV
PCSPPCProtectionInterfacesPQMSystemType D
Operating ranges
7 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Continuous frequency range | 49.0–51.0 Hz | PCS | |
| Extended frequency (30 min) | 47.5–49.0 Hz and 51.0–51.5 Hz | PCS | §6 |
| Continuous voltage range (≤ 1 kV) | 0.85–1.10 × Un | PCS | §6 |
| Continuous voltage range (> 1 kV) | 0.90–1.10 × Uc | PCS | §31 |
| RoCoF withstand | ± 2 Hz/s | PCS | |
| Phase jump withstand | Up to 20° transitory | PCS | |
| Permissible P reduction at underfrequency | Up to 6% of Pn per Hz below 49 Hz | PCS | §12 |
Fault ride-through
6 requirementsUV-FRT profiles differ between distribution-connected (Type B/C) and transmission-connected (Type D/transmission) facilities, and between DK1 and DK2 synchronous areas for transmission connections.
| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| OV-FRT | 1.20 × Uc for 5s, 1.15 × Uc for 60s | PCS | |
| UV-FRT — distribution (Type B/C) | 0.15 pu for 250 ms → 0.90 pu at 1.5s | PCS | |
| UV-FRT — transmission DK1Type D | 0.00 pu for 150 ms → 0.85 pu at 1.5s | PCS | |
| UV-FRT — transmission DK2Type D | 0.00 pu for 150 ms → 0.90 pu at 1.5s | PCS | |
| Consecutive faults | New dip after recovery = new fault situation | PCS | §114 |
| Successive faults beyond profile | Disconnection permitted if faults push beyond time limit | PCS | §114 |
Fast fault current (FFC)
5 requirementsNon-synchronous facilities must supply reactive fault current during voltage dips. Distribution-connected Type B/C use a single FFC profile; transmission-connected facilities have separate DK1 and DK2 profiles.
| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| FFC activation — distribution | Commence within 100 ms after voltage dip | PCS | |
| FFC characteristic — distribution | Linear 0.9 → 0.5 Uc, tolerance ±20% of In | PCS | §115 |
| FFC activation — transmission DK1Type D | Commence within 100 ms, linear 0.9 → 0.5 pu | PCS | §133 |
| FFC activation — transmission DK2Type D | Commence within 100 ms, linear 0.9 → 0.5 pu | PCS | §134 |
| Delayed exit from FRT state | 100–500 ms configurable, default 250 ms for distribution | PCS |
Post fault active power recovery
5 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| PFAPR — Type B/C | Resume pre-fault P within 5s, ± 5% Pn tolerance | PCS | |
| PFAPR gradient | Approximately constant gradient, within bounds | PCS | §117 |
| PFAPR precision | ± 5% of Pn | PCS | §117 |
| Extended PFAPR — Type DType D | Resume pre-fault P within 5–20s (configurable, 1s steps) | PCS | |
| Extended PFAPR max rampType D | ≤ 25% Pn per second | PCS | §124 |
Active power control and frequency control
20 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Absolute power constraint function | Implemented within 10s of receipt, ≤ 2% Pn precision (1 min avg) | PPC | |
| Power constraint resolution | ≥ 1% of Pnl and Pno | PPC | §9 |
| Ramp rate range | 1–20% Pn/min, max 1 MW/s | PPC | |
| Default ramp rate | Maximum gradient | PPC | §32 |
| Connection gradient | 20% Pn/min, max 1 MW/s | PPC | |
| LFSM-O — DK1 | Breakpoint 50.20 Hz, droop 5%, range 2–12% | PPC | |
| LFSM-O — DK2 | Breakpoint 50.50 Hz, droop 4%, range 2–12% | PPC | §23 |
| LFSM-O timing | Commence ≤ 2s, fully supplied within 30s | PPC | §23 |
| LFSM-O precision | ≤ 5% Pn (1 min avg), sensitivity ≤ 10 mHz | PPC | §23 |
| LFSM-O island detection delay | 500 ms before downward adjustment (distribution) | PPC | §23 |
| LFSM-U — DK1 | Breakpoint 49.80 Hz, droop 5%, range 2–12% | PPC | |
| LFSM-U — DK2 | Breakpoint 49.50 Hz, droop 4%, range 2–12% | PPC | §52 |
| LFSM-U timing | Commence ≤ 2s, fully supplied within 30s | PPC | §52 |
| LFSM-U disconnect (cannot reverse) | DK1: 49.00 Hz, DK2: 48.80 Hz | PPC | §52 |
| FSM band — DK1 | 49.80–50.20 Hz | PPC | §53 |
| FSM band — DK2 | 49.50–50.50 Hz | PPC | §53 |
| FSM droop | 2–12% in 1 pp steps | PPC | §53 |
| FSM active power range | 1.5–10% of Pn as minimum | PPC | §53 |
| FSM sensitivity | ≤ 10 mHz | PPC | §53 |
| Auto connection within FSM band | ≥ 3 min after voltage returns to normal range | PPC | §7 |
Reactive power and voltage control
11 requirementsType C requires Q control, PF control, and voltage control. The relevant system operator specifies which control function is activated and the specific settings.
| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Q control — setpoint response | Applied within 2s, complete within 30s | PPC | |
| Q control — precision (Type C) | ± 3% of Qn (1 min avg), 100 kvar resolution | PPC | §55 |
| Q control — precision (transmission)Type D | 5 MVAr or 5% Qn (lesser), same for resolution | PPC | §130 |
| PF control — setpoint response | Applied within 2s, complete within 30s | PPC | §56 |
| PF control — precision (Type C) | ± 3% of Qn, resolution 0.01 | PPC | §56 |
| Voltage control — step response | 90% within 1s, 100% within 5s | PPC | |
| Voltage control — droop | 2–7%, resolution 0.5% | PPC | §57 |
| Voltage control — deadband | ± 5% of Uref, step ≤ 0.5% Uref, symmetrical | PPC | §57 |
| Voltage control — precision | ± 3% of Qn (1 min avg) | PPC | §57 |
| Infrastructure Q compensation | Compensate facility reactive power when disconnected/idle | System | §54 |
| Units out for service | Q may be reduced pro rata with units out of operation | System | §38 |
System protection
4 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| System protection levels | 5 levels: 70%, 50%, 40%, 10%, 0% of rated power | Protection | |
| Activation time | Begin within 1s, fully effected within 10s | Protection | §58 |
| 0% level | Without disconnection from electricity supply system | Protection | §58 |
| Precision | ≤ 1% of setpoint (1 min avg) | Protection | §58 |
Protection settings
11 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| OV step 3 (Type C/D) | 1.20 × Uc → 100 ms trip | Protection | §59 |
| OV step 2 | 1.15 × Uc → 200 ms trip | Protection | §59 |
| OV step 1 | 1.10 × Uc → 60s trip | Protection | §59 |
| UV step 1 | 0.90 × Uc → 60s trip | Protection | §59 |
| Overfrequency | 51.5 Hz → 200 ms trip | Protection | §59 |
| Underfrequency | 47.5 Hz → 200 ms trip | Protection | §59 |
| Rate of change of frequency | ± 2.5 Hz/s → 80 ms trip | Protection | §59 |
| Internal fault protection | Selective with grid protection, ≤ 100 ms trip for short circuits | Protection | |
| Priority order | 1. Grid/equipment → 2. Synthetic inertia → 3. Frequency control → 4. Power constraint → 5. Gradient | Protection | §26 |
| Vector jump relays | NOT allowed as island protection | Protection | §25 |
| Post-commissioning changes | DSO/Energinet may require protection setting changes | Protection | §24 |
Power quality
9 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| DC current injection | < 0.5% of rated current | PQM | §14 |
| Rapid voltage changes (≤ 33 kV) | d ≤ 4% of Un | PQM | §16 |
| Rapid voltage changes (> 33 kV) | d ≤ 3% of Un | PQM | §16 |
| Flicker — Type C/D | Per limits set by relevant system operator | PQM | §47 |
| Harmonics — Type C/D | Per voltage limits set by relevant system operator | PQM | §48 |
| Interharmonics — Type C/D | Per voltage limits set by relevant system operator | PQM | §49 |
| 2–9 kHz distortions — Type C/D | Per limits set by relevant system operator | PQM | §50 |
| Three-phase balance (> 1 kV) | Must be balanced — no voltage unbalances | PQM | §40 |
| PQ measurement standard | DS/EN 61000-4-30 (class A) | PQM | §22 |
Power oscillation damping (POD)
4 requirementsType C non-synchronous facilities must be capable of power oscillation damping. This ensures converter-based BESS does not introduce or amplify oscillations in the grid.
| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Oscillation limit | ≤ ±0.5% of current power or ±0.25% of Pn (least restrictive) | PCS | |
| Damping time | Within 180 seconds of exceeding limit | PCS | §121 |
| Applicability | All voltages within normal and time-limited ranges | PCS | §121 |
| After repeated incidents | Damped within 180s after last incident | PCS | §121 |
Information exchange and SCADA
12 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Basic signals (≥ 0.8 kW) | Stop signal, Hold signal in PCOM | Interfaces | §27 |
| Logic interface | Input port for commands — can be controlled remotely | Interfaces | §27 |
| Extended signals (≥ 1 MW) | CB status, P, Q, PF, control modes, setpoints — Table 20 | Interfaces | |
| Online communication (≥ 1 MW) | Real-time or periodic, UTC timestamps ±1 ms | Interfaces | §43 |
| Type C additional signals | Planned P, voltage, V-control droop/status, system protection | Interfaces | §60 |
| Type D additional signalsType D | Available P up/down, available Q up/down | Interfaces | §65 |
| Measurement precision — MW | 1.0% (Type C), 0.5% (Type D) | Interfaces | §43 |
| Measurement precision — MVAr | 2.0% (Type C), 1.0% (Type D) | Interfaces | §65 |
| Measurement precision — kV | 1.0% (Type C), 0.5% (Type D) | Interfaces | §65 |
| IEC 61850 communication | Required for new exchanges; deadline may be extended | Interfaces | |
| Setpoint logging (≥ 1 MW) | Record all changes + issuer, ≥ 100 changes, ≥ 3 months | Interfaces | §41 |
| Timestamp precision | 10 ms or less, referenced to UTC | Interfaces | §42 |
Fault incident recording
8 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Required measurements | Voltage, current, P, Q, frequency per phase + protection activations | PQM | |
| Slow scan (3–25 MW) | 50 Hz RMS, −10s to +60s | PQM | §62 |
| Slow scan (≥ 25 MW) | 50 Hz RMS, −10s to +60s | PQM | §62 |
| Fast scan (10–25 MW) | ≥ 1 kHz, −0.25s to +2.75s | PQM | §62 |
| Fast scan (≥ 25 MW) | ≥ 1 kHz, −3s to +60s | PQM | §62 |
| Storage | ≥ 3 months, up to 100 incidents | PQM | §62 |
| Timestamp | UTC, ≤ 10 ms precision | PQM | §62 |
| Format | COMTRADE, accessible to system operator on request | PQM | §41 |
Type D additional requirements
6 requirementsType D adds island mode, quick re-synchronisation, simulation models, and authorised automatic connection on top of all Type C requirements.
| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Automatic connection authorisationType D | Not permitted without system operator authorisation | PPC | |
| Island mode capabilityType D | Operate within normal f/V ranges and FSM bands | PCS | |
| Quick re-synchronisationType D | As instructed by system operator | PCS | |
| Household operation (> 15 min re-sync)Type D | Self-sustained from any operating point, no external supply needed | PCS | §64b |
| Simulation modelsType D | Equivalent to NC RfG / NC DC requirements | System | |
| Extended PFAPR optionType D | System operator chooses standard or extended PFAPR | PCS | §124 |
Compliance testing (non-synchronous Type C/D)
10 requirementsProduct certificates from an approved certification body may substitute for any individual test. The relevant system operator may require additional tests beyond those listed here.
| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| 1. LFSM-O | Frequency steps/ramps ≥ 10% Pmax change, droop verification | PPC | §142 |
| 2. Active power controllability | Demonstrate operation below reference point per absolute constraint | PPC | §143 |
| 3. LFSM-U | Frequency steps/ramps ≥ 10% Pmax, starting at ≤ 80% of max | PPC | §143 |
| 4. FSM | Full frequency range, droop/deadband/sensitivity verification | PPC | §143 |
| 5. Frequency restoration control | Demonstrate cooperation between FSM and frequency restoration | PPC | §143 |
| 6. Reactive power supply | Max Q at ind/cap, at >60%, 30–50%, and 10–20% power levels | System | §143 |
| 7. Voltage control | Droop, deadband, precision, rise time verification | PPC | §143 |
| 8. Q control | Range, rise, precision, response time | PPC | §143 |
| 9. Power factor control | Range, precision, reactive response to P step change | PPC | §143 |
| Type D: same as Type C testsType D | All Type B + C compliance tests required | PPC | §144 |
Compliance simulation (non-synchronous Type C/D)
9 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| LFSM-O simulation | Validate model against test, demonstrate compliance | System | §148 |
| FFC simulation | Demonstrate fast fault current per FFC requirements | System | §148 |
| UV-FRT / OV-FRT simulation | Demonstrate voltage fault tolerance | System | §148 |
| PFAPR simulation | Demonstrate active power recovery after fault | System | §148 |
| LFSM-U simulation | Validate model, demonstrate low-frequency response | System | §149 |
| FSM simulation | Full frequency range, validate against tests | System | §149 |
| Reactive power simulation | Validate model against reactive power tests | System | §149 |
| POD simulation | Demonstrate power oscillation damping capability | System | §149 |
| Type D: voltage fault toleranceType D | Model must demonstrate UV-FRT + OV-FRT compliance | System | §150 |
Grid connection permit process
| Stage | Applies to | Details |
|---|---|---|
| Installation document | Type A | Location, date, max power, energy source, product certificates — submit to DSO |
| Facility document + declaration of conformity | Type B/C | Protection agreements, technical data, product certificates, simulation models, compliance test reports — DSO issues FON |
| EON (Energisation Operational Notification) | Type D | Permission to energise internal grid and auxiliary supplies via POC |
| ION (Interim Operational Notification) | Type D | Permission to operate and test for up to 24 months. Requires declaration of conformity, technical data, simulation models, test plans |
| FON (Final Operational Notification) | Type D | Full operational permit after all ION incompatibilities resolved. Updated models and test results with actual measured values |
| LON (Limited Operational Notification) | All (post-FON) | If significant modification or capacity loss lasts > 3 months. Max 12 months, suspends FON for affected requirements |
Requirements based on Technical Regulation 3.3.1 Revision 6, published by Energinet (14 February 2025, English translation). Effective from 1 May 2025.