FIFingrid
SJV2024 — Finland Grid Code
161 grid connection requirements for BESS plants, organized by functional category. Each requirement is tagged with the equipment scope responsible for delivering it. Focus on Type C (10–30 MW) and Type D (≥30 MW or ≥110 kV).
Type categories (Table 3.1)
Type A
0.8 kW – 1 MW
Type B
1 – 10 MW
Type C
10 – 30 MW
Type D
≥ 30 MW or ≥ 110 kV
PCSPPCProtectionInterfacesPQMSystemType D
Operating ranges
6 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Continuous voltage rangeType D | 90–105% of nominal | PCS | §10.5.2 |
| Continuous frequency range | 49.0–51.0 Hz | PCS | §10.2.1 |
| Extended frequency (30 min) | 47.5–49.0 Hz and 51.0–51.5 Hz | PCS | §10.5.2 |
| Extended voltage (60 min) | 105–110% | PCS | §10.5.2 |
| RoCoF withstand | ≥ 2.0 Hz/s | PCS | §10.2.2 |
| Phase jump withstand | ± 30° permanent vector shift | PCS | §10.3.2 |
Fault ride-through
7 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Undervoltage FRT — Type B/C | 0.05 pu for 150 ms → 0.85 pu at 0.75s → 0.90 pu at 1.5s | PCS | §10.3.2 |
| Undervoltage FRT — Type DType D | 0.00 pu for 200 ms → 0.85 pu at 0.75s → 0.90 pu at 1.5s | PCS | §10.5.3 |
| Overvoltage withstand | 1.20 pu (3.5s) → 1.15 pu (5s) → 1.10 pu (10s) | PCS | §10.3.3 |
| Overvoltage extendedType D | 1.10 pu for 60 min total | PCS | §10.5.4 |
| Applicable fault types | 3-phase, 2-phase, 2-phase-earth, 1-phase-earth | PCS | §10.3.2 |
| Consecutive faults | Must ride through — no auto-disconnect | PCS | §10.3.2 |
| Active power recovery | Within 3 seconds to pre-fault level (± 5%) | PCS | §10.3.5 |
Reactive current supply (fault current)
7 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Default k-factor | 2.5 (configurable 2–6) | PCS | §10.3.4 |
| Current priority during fault | Iq over Ip outside normal voltage range | PCS | §10.3.4 |
| Activation — undervoltage | < 0.85 pu activate; > 0.90 pu deactivate | PCS | §10.3.4 |
| Activation — overvoltage | > 1.10 pu activate; < 1.05 pu deactivate | PCS | §10.3.4 |
| Rise time to 90% | 30–50 ms | PCS | §10.3.4 |
| Target accuracy | +20% / −10% within 80 ms | PCS | §10.3.4 |
| Negative sequence (asymmetric faults) | Must supply in ratio defined by k-factor | PCS | §10.3.4 |
Grid-forming capability
11 requirementsMandatory for Type C and D. Must operate constantly in grid-forming mode — not switchable. Active at all operating points, all charge states, production and demand modes.
| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Operating mode | Constantly in grid-forming mode | PCS | §10.4.3 |
| Operational scope | All operating points, all SoC, production + demand | PCS | §10.4.3.1 |
| Vector shift response | Resist phase jump — supply P and Q instantaneously | PCS | §10.4.3.2 (1a) |
| Voltage amplitude response | Supply Q to reinforce voltage stiffness | PCS | §10.4.3.2 (1b) |
| Response speed | Current change within a few milliseconds | PCS | §10.4.3.2 (1c) |
| Current limiting coordination | Must not cause GFM discontinuity | PCS | §10.4.3.1 (f) |
| Island operation | Seamless transition to island and back | PCS | §10.4.3.2 (2) |
| Oscillation damping | Must dampen: 0.2–1 Hz, 1–15 Hz, 15–45 Hz | PCS | §10.4.3.2 (3) |
| Negative sequence current | Must supply to maintain voltage symmetry | PCS | §10.4.3.2 (4) |
| Coordination with PPC | GFM fast response + PPC slower cascade to final value | PPC | §13.2.2 |
| No overdimensioning required | GFM must not require oversizing | PCS | §10.4.3.1 |
Active power control and frequency control
23 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Active power setpoint accuracy | ± 3% of rated capacity (10s avg, ≤ 5 MW) | PPC | §11.3.5 |
| Setpoint resolution | ≥ 0.1 MW | PPC | §11.3.3.1 |
| Active power limiters | Below rated, both modes, 0.1 MW resolution | PPC | §11.3.3.1 |
| Rated capacity must not be exceeded | Not even momentarily — protective device if needed | Protection | §11.3.2.1 |
| Over-capacity trip | 5% for 20s or 20% for 1s | Protection | §11.3.2.1 |
| Ramp rate range | 0.1 × Pmax/min to 1.0 × Pmax/min (min 1 MW/min) | PPC | §11.3.3.2 |
| Default ramp rate | 100% of rated capacity per minute | PPC | §11.3.3.2 |
| Linear change | No stepwise changes > 5% | PPC | §11.3.3.2 |
| Separate up/down ramp setpoints | Must be configurable separately | PPC | §11.3.3.2 |
| Start-up voltage impact | Connection must not cause > 3% voltage change | System | §11.3.2.2 |
| LFSM-O activation | > 50.5 Hz, droop 2–12% (rec. 4%), delay ≤ 2s | PPC | §11.1.2 |
| LFSM-O always enabled | Cannot be turned off | PPC | §11.1.2 |
| LFSM-O overrides | Prevails over all other active power setpoints | PPC | §11.1.2 |
| LFSM-U activation | < 49.5 Hz (demand mode: reduce demand), droop 2–12% | PPC | §11.3.3.4 |
| LFSM-U always enabled | Cannot be turned off | PPC | §11.3.3.4 |
| FSM droop | 2–12% in 1 pp steps, default 4% | PPC | §11.3.3.3 |
| FSM deadband | 0.00–0.50 Hz in 0.01 Hz steps | PPC | §11.3.3.3 |
| FSM power range | 0–100% × Pmax, 0.1 MW steps, asymmetric possible | PPC | §11.3.3.3 |
| FSM per-range droop | Different droop per frequency range | PPC | §11.3.3.3 |
| FSM on/off per range | Can toggle frequency control per range | PPC | §11.3.3.3 |
| Frequency sensitivity | ≥ 10 mHz | PPC | §11.3.5 |
| Frequency control start delay | ≤ 2 seconds on step change | PPC | §11.3.5 |
| Mode transitions | No sudden P or Q changes | PPC | §11.3.4 |
Reactive power capacity
10 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Q/Pmax,p ratio | ± 0.33 (cos φ = 0.95) | System | §12.2.1 |
| Measurement point | Connection point (primary) or HV side of main trafo | System | §12.2.1 |
| Voltage range for full Q | 0.90–1.05 pu | System | §12.2.1 |
| Applies across entire P range | Full rated production and demand capacities | System | §12.2.1 |
| Supplementary Q | May be required if CP not at HV terminals | System | §12.2.2 |
| Separate compensation devices | Allowed — not limited to PCS only | System | §12.2.3 |
| Switchable capacitor banks | NOT allowed for meeting Q requirement | System | §12.2.3 |
| Q capacity calculation | Deliver at Stage 1 to RNO | System | §12.2.4 |
| Operating points for Q calc | 5 voltages (0.85–1.10 pu) × 4 power levels | System | §12.2.4 |
| Q must not be artificially limited | Software must not restrict; limiters documented | PPC | §12.2.5 |
Voltage and reactive power control
18 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Three modes required | Constant voltage, constant Q, constant PF | PPC | §13.2.1 |
| Primary mode | Constant voltage control | PPC | §13.2.1 |
| Voltage setpoint resolution | ≤ 0.1 kV steps | PPC | §13.2.2 |
| Voltage setpoint ramp | ≤ 0.1 kV/s average rate of change | PPC | §13.2.2 |
| Voltage droop (slope) | 2–7% in ≤ 0.5 pp steps | PPC | §13.2.2 |
| Step response (0→80%) | ≤ 1 second | PPC | §13.2.2 |
| Overshoot limit | ≤ 15% of total Q change | PPC | §13.2.2 |
| Settling time | ≤ 5 seconds | PPC | §13.2.2 |
| Steady-state accuracy | ± 5% of target Q value | PPC | §13.2.2 |
| Cascade with GFM | GFM fast initial → PPC guides to final value | PPC | §13.2.2 |
| Constant Q accuracy | ± 2% of rated Q (tol. ± 0.5%) | PPC | §13.2.3 |
| Constant Q rise time | 10s (± 1s) for ± 30% rated Q step | PPC | §13.2.3 |
| Constant Q setpoint steps | ≤ 0.5% of rated Q (max 1 Mvar) | PPC | §13.2.3 |
| Constant PF accuracy | ± 0.005 (tol. ± 0.002) at > 50% rated | PPC | §13.2.4 |
| Constant PF setpoint steps | ≤ 0.005 between 0.95ind and 0.95cap | PPC | §13.2.4 |
| No voltage deadbandType D | Type D: deadband not allowed | PPC | §13.3 |
| POD (Power Oscillation Damping)Type D | May be required if oscillations affected | PPC | §13.3 |
| Fallback: central controller lost | RO disconnects (partial or full) | PPC | §13.2.5 |
Remote control and SCADA interfaces
11 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Fingrid electronic control connection | Owner implements; SCADA interface to RO | Interfaces | §10.4.1.1 |
| Response time — mode/setpoint change | Implemented within 1 minute | Interfaces | §10.4.1.1 |
| Reach new operating point (P, Q) | ≤ 15 minutes after Fingrid request | Interfaces | §10.4.1.1 |
| Control signals from Fingrid | 15 signals: P, Q, ramp rates, V/Q mode, droop, FSM, system state | Interfaces | Table 10.1 |
| Status signals to Fingrid | 6 signals: ack, status, SoC, P avail, Q avail, remote status | Interfaces | Table 10.2 |
| Direct control bus interface | Input port for direct Fingrid control (per-project decision) | Interfaces | §10.4.1.2 |
| RNO control commands | May specify additional remote control and status signals | Interfaces | §10.4.1.3 |
| RO designation | Owner must designate a Relevant Operator | Interfaces | §10.4.1 |
| RO availability | 24/7 | Interfaces | §10.4.1.4 |
| Continuous monitoring | Controllability and telecom connections — without delay | Interfaces | §10.4.1.4 |
| Periodic testing | Remote operation connections tested periodically | Interfaces | §10.4.1.4 |
Energy and state management
13 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| SoC / energy available | Report to Fingrid (% or MWh) | PPC | Table 10.2 |
| Active power capacity available | MW, separately for production and demand | PPC | Table 10.2 |
| Reactive power capacity available | Mvar, separately for inductive and capacitive | PPC | Table 10.2 |
| Per-unit reporting | If capacity unevenly distributed across units | PPC | §11.3.2.1 |
| Temperature dependence | Report how ambient temp affects capacity | PPC | §11.3.2.1 |
| LFSM-U zero-transfer hold | Hold at P = 0 until f > 49.5 Hz | PPC | §11.3.3.4 |
| No disconnect during LFSM-O | Down-regulation must not trip BESS or modules | PPC | §11.1.2 |
| Autonomous connection — frequency | 49.0–51.0 Hz | PPC | §10.4.2 |
| Autonomous connection — voltage | Within normal range | PPC | §10.4.2 |
| Autonomous connection — remote | Remote operation connection must be functioning | PPC | §10.4.2 |
| Loss of control — individual unit | Continue at last setpoints unless agreed otherwise | PPC | §10.4.1.4 |
| Control not restored within 2 hours | Must be manned or disconnected | PPC | §10.4.1.4 |
| Recovery from network loss | Must not cause factory resets or config loss | PPC | §10.2.6 |
Protection
10 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Priority ranking | 1. Network + equipment → 2. P/f control → 3. Power restriction → 4. Gradient | Protection | §10.3.6 |
| Settings responsibility | Owner specifies; coordinated with RNO | Protection | §10.2.5 |
| Must not conflict with grid code | Settings shall not prevent FRT or other functions | Protection | §10.3.6 |
| RoCoF protection — Type C/D | BANNED — must not use RoCoF relays | Protection | §10.4.8 |
| RoCoF protection — Type A/B | Allowed only if threshold ≥ 4 Hz/s for ≥ 250 ms | Protection | §10.2.5 |
| Vector shift protection | Only for < 50 kW; trigger ≥ 15° | Protection | §10.2.5 |
| Recommended anti-islanding | Frequency and voltage measurement based | Protection | §10.2.5 |
| Overvoltage limiters | Direct and delay-free during high voltage | Protection | §13.2.6 |
| Current limiter coordination | Maximise Q utilisation without trip risk | Protection | §12.2.5 |
| Main transformer neutral earthing | Per RNO specifications | Protection | §10.4.6 |
Telecommunications and cybersecurity
4 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Cybersecurity responsibility | Owner responsible for all telecom and control systems | Interfaces | §10.3.7 |
| Unauthorized access prevention | Control system + all remote access connections | Interfaces | §10.3.7 |
| Supply chain cybersecurity | External providers (equipment suppliers, RO) must comply | Interfaces | §10.3.7 |
| InfoSec report to Fingrid | Report on information security and telecom connections | Interfaces | §10.3.7 |
Black start and island operation
4 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Black start capability | Notify RNO if BESS can be used for black start | System | §10.4.7 |
| Island operation arrangements | Agree planned and disturbance island scenarios with RNO | System | §10.4.7 |
| Unplanned island prevention | Based on network status signals and protective devices | Protection | §10.4.7 |
| GFM intrinsic island capability | Grid-forming converters inherently capable | PCS | §10.4.3.2 (2) |
Power quality monitoring and instrumentation
6 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| PQ assessment before connection | Deliver PQ impact reports to RNO | PQM | §10.4.5 |
| Harmonic emission limits | Per Fingrid "Power quality in 110 kV grid" | PQM | §10.4.5 |
| Type C instrumentation | Per §9.3 | PQM | §9.3 |
| Type D instrumentation | Per §9.4 | PQM | §9.4 |
| Commissioning test sampling | ≥ 1 kHz sampling, ≥ 50 Hz recording | PQM | §15.3.1 |
| Voltage control test sampling | ≥ 2 kHz at one converter module | PQM | §15.3.1 |
Commissioning tests (Type C/D — 16 tests)
16 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| 1. LFSM-O | Frequency steps/ramps ≥ 10% Pmax change, droop 4%, prod + demand | PPC | §15.3.4 (1) |
| 2. LFSM-U | Frequency steps/ramps ≥ 10% Pmax change, prod + demand | PPC | §15.3.4 (2) |
| 3. Frequency sensitive mode (FSM) | Full frequency range, ± 10% Pmax, droop/deadband per range | PPC | §15.3.4 (3) |
| 4. Rate of change of active power | At 0.1 × Pmax/min and max rate, prod + demand | PPC | §15.3.4 (4) |
| 5. Constant voltage control | Step response at slope 2% and 4%, internal + external voltage changes | PPC | §15.3.4 (5) |
| 6. Constant reactive power control | Stepwise Q changes, 0.3 × Qn steps, setpoint + ramp rate demo | PPC | §15.3.4 (6) |
| 7. Constant power factor control | PF steps of 0.02, rise time demo, setpoint + ramp rate demo | PPC | §15.3.4 (7) |
| 8. Reactive power capacity + P restriction | 4 operating points × max ind/cap, 15–30 min per point | System | §15.3.4 (8) |
| 9. Starting and stopping | No quality deviations in RNO network | System | §15.3.4 (9) |
| 10. Voltage control disturbance | Mode change on measurement loss — all planned modes verified | PPC | §15.3.4 (10) |
| 11. Remote control | All control locations, signal priority, automated fallback functions | Interfaces | §15.3.4 (11) |
| 12. Autonomous connection after network loss | Return to local control, no config reset, reconnect when authorised | PPC | §15.3.4 (12) |
| 13. Stable operation with PPMs | Stable alongside other grid-connected facilities | PCS | §15.3.4 (13) |
| 14. Fault ride-through | Per §10.3.2 (Type C) or §10.5.3 (Type D) profiles | PCS | §15.3.4 (14) |
| 15. Island mode | Seamless transition and resynchronisation | PCS | §15.3.4 (15) |
| 16. Angle jump | Operate under stepwise network voltage angle change | PCS | §15.3.4 (16) |
Simulation models and dynamic studies
15 requirements| Requirement | Specification | Scope | Ref |
|---|---|---|---|
| Model formats | PSS®E and PSCAD™ (separately) | System | §16.1.1 |
| Model scope | Converters, compensation, controllers, limiters, protection | System | §16.1.1 |
| Model aggregation | Single equivalent generator per sub-system of similar units | System | §16.1.2 |
| Power flow simulation | P-V dependence, voltage profiles, fault currents | System | §16.1.3 |
| PSS®E time resolution | 10 ms – 10 s (rapid change) | System | §16.1.4 |
| PSCAD time resolution | 0.4 ms – 10 s (very rapid change) | System | §16.1.4 |
| Model verification | Compare simulation vs commissioning test results | System | §16.1.5 |
| Documentation | Block diagrams (P/f, V/Q, other controls), parameters, instructions | System | §16.1.5 |
| Type D — stability impactType D | Electromechanical oscillations and converter-based stability | System | §16.1.6 |
| Type D — HIL testingType D | Fingrid may require Hardware-in-the-Loop verification | System | §16.1.6 |
| Dynamic study: voltage disturbance | PSS®E + PSCAD at A4, A5 | System | §14.1.1 |
| Dynamic study: constant voltage control | PSS®E + PSCAD at A1–A5 | System | §14.1.2 |
| Dynamic study: network vector shift | PSCAD at A4, A5 | System | §14.1.3 |
| Dynamic study: island operation | PSCAD at A4, A5 | System | §14.1.4 |
| Dynamic study: impedance scan | PSCAD at A1–A5 (1–300 Hz) | System | §14.1.5 |
Compliance process timeline
| Stage | Timing | Deliverables |
|---|---|---|
| Stage 1 | Before connection agreement | Technical data, reactive power calculation, preliminary simulation models |
| Dynamic studies | 6 months before first power supply | Study results + simulation models to RNO and Fingrid |
| Test plan | 2 months before commissioning | Test plan, preliminary instructions, practical arrangements |
| Pre-test meeting | 2 months before commissioning | Agree final test plan with RNO and Fingrid |
| Commissioning | Before commercial operation | 16 tests (Type C/D), 90% of converters operational |
| Model verification | After commissioning | Compare simulation vs test results, deliver verification report |
Requirements based on SJV2024 as published by Fingrid (15.1.2025, unofficial English translation).